Casebook Component – Termination for Delay, Affirmation, R&W, Election
Termination for Delay
Contracts normally specify a time at which the obligations are to be performed.
Where no time is specified for performance the law implies an obligation to perform within reasonable time
When is time of the essence?
Traditionally only equity did not presume that time stipulations were of the essence, but with the Judicature Acts this is now the prevailing view
If time was not of the essence, the party in breach was prevented from terminating and ordering specific performance
If time was of the essence, either by express provision or because of the nature of the subject matter, the parties would be left to their common law rights
Where time is not of the essence
Where time is not of the essence the aggrieved party may claim damages but not a right to terminate
This right to terminate will be available if the delay continues so long as to amount to repudiation or serious breach of an innominate term (Laurinda Pty Ltd v Capalaba Park Shopping Centre (1989) 166 CLR 623)
Notice
Where one party is in breach and time is not of the essence, the aggrieved party can gain a right to terminate through notice, which, if not performed by the party in breach, will give the aggrieved party a right to terminate. The notice must:
The notice must specify a time for performance
The time allowed must be reasonable
It must clearly convey that either the time fixed for performance is of the essence OR that the party giving notice will regard themselves as being entitled to terminate for non-compliance
Louinder v Leis (1982) 149 CLR 509 Facts: By a contract dated 1/11/79 the vendor (Louinder) sold property to the purchaser (Leis). No date was fixed for completion and time was not stated to be of the essence. Cl 4 obliged the purchaser to tender a transfer to the vendor for execution within 28 days of receipt of the title. The statement was delivered the next day. The parties agreed to settle early in the following year but the vendor sought delay in settlement for three months. The purchaser agreed but was then informed that the vendor required settlement within a week. On the 8th of February, no tender of a transfer being made by the purchaser, the vendor issues a notice for completion within 21 days. On 4th March the contract was terminated and an attempt on the 14th of April to complete by the purchasers rejected. The purchaser sued for specific performance Chief Justice Gibbs disposed of the case on the ground that Cl 4 could not be relied on for the first time on appeal. This meant that the appellant was not entitled to give notice requiring completion unless the respondent was guilty of unreasonable delay – which it was not in this case. But in obiter... Issue: Whether, if the appellant established that the respondent was in breach of cl 4, it would have been open for him to give a notice to complete. Obiter (Gibbs CJ):
|
---|
Laurinda v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623 Facts: On 31/10/85, the respondent lessor (C) and the appellant lessee (L) entered into an agreement for lease of a shop forming part of a retail centre. The lease was silent on matters such as commencement date but made provision for its ascertainment which was then 12/1985. On 3/12 L went into possession of the shop and in 1/86 paid $2317 for stamping costs as required by the lease. In 3/86 L’s accountants requested C’s solicitors to forward a copy of the lease at the earliest opportunity. On 25/3 the solicitors advised that in 10/85 the lease was sent to Melbourne for execution by C and was expected “in the near future”. By 4/86 C was aware that L wished to sell the business. On 21/8 L’s solicitors wrote to C’s solicitors pointing out that the lease should have been registered 10 months ago and L had already provided funds for its registration and explained its importance. The letter stipulated that in – ‘in view of the delay it was reasonable to require registration be completed in 14 days and if not L would reserve their rights in respect of the default. The letter was received the following day by C’s solicitors and on 3/9 they replied that it had been sent to C for instructions. On 5/9 L terminated on the ground that C repudiated or was in breach of essential terms as a result of C’s failure to register/deliver the lease in registrable form. On 3/10 C re-entered the premises. On 31/10 L commenced an action for declaration that the lease was validly rescinded and for recovery of $2317 and damages and interest. C denied it was guilty of unreasonable delay in completing and contended that L’s purported termination was wrongful repudiation and claimed unpaid rent, damages and interest. Case History: At trial Connolly J held that the letter of 21/8 was not effective notice to complete but that termination was valid for C’s repudiation. The Full Court on appeal held that it had not, L appealed to the High Court. Issue: Whether or not the letter of 21/8 was valid notice Ratio (Deane and Dawson JJ):
Issue 2: Even if the letter of 21/8 was inadequate to make time of the essence, was the lessee entitled by 5/9 to rescind to the contract for repudiation by the lessor Ratio (Deane and Dawson JJ):
Order: Appeal allowed, orders of the Full Court of the Supreme Court set aside and the orders made by the primary judge restored |
---|
Affirmation
The Right to Elect
On breach justifying termination, the aggrieved party has a right to terminate – that is, it is put to his or her election
The essence of election is that the aggrieved party cannot take two inconsistent positions, it must terminate or affirm
Where the contract is...