Causation & Remoteness, Mitigation
Stuart v Condor Commercial Insulation Pty Limited [2006] NSWCA 334 Relevant Facts: Stuart (S) was a construction company who contracted with the Commonwealth to replace insulation in a number of residential Sydney properties under the SANIP. The appellant then sub-contracted this work to the respondents (C) with each property subject to a separate agreement. SANIP cancelled its contract with S after a fire broke out in one of the properties due to C’s negligence (in not boxing the down lights). S brought proceedings against C, claiming damages for the loss of profits that followed its termination of contract with SANIP and consequent inability to secure contracts for future houses under the program. Issue: What is the approach to remoteness under the second limb of the test in Hadley v Baxendale Decision: Under the second limb the following matters require determination:
Ratio (Beazley JA):
Conclusion on remoteness – above Was the loss in the reasonable contemplation of the parties (Ratio):
Was the event that caused the loss one that was ‘not unlikely to occur’?
Ipp JA also commented that Stuart was responsible for the workmanship of anyone they chose to sub-contract and if it complied with this obligation it would have ensured that the down-lights were boxed. Also relevant was that the representative of Stuart also failed to detect the presencde of down-lights and this was a cause of breach of contract with SANIP. He said that it would not have been within C’s contemplation that not only it would breach but S would also breach its contract. The trial judge’s finding that all agreed it would ignite was errorneous – not taking into account C’s witness. The effect of this is that their belief in the non-inflammable qualities of the material, they did not contemplate a breach in not booxing the down lights Order: Appeal dismissed |
---|
Mitigation of Damage
Reasonable steps in mitigation and the impecunious plaintiff
Burns v MAN Automotive (Aust) Pty Ltd (1986) 161 CLR 653 Relevant Facts: The appellant (B) bought a prime mover from the respondent (M). The respondent warranted that the engine was fully reconditioned knowing that the vehicle was intended to be used in business and he should have known that he was not in affluent circumstances. On 7/1978 the appellant learned that the engine was not fully reconditioned and was defective at purchase. M wouldn’t rectify it even though pressed to do so by B. B couldn’t afford to pay the $7-8k required to bring it to its warranted condition. The defective state of the engine meant it could not travel on interstate routes. Accordingly, until the end of ’79, B used it within his own state to carry business at a loss. At the end of ’79 the vehicle broke down again and was repossessed by the finance company. Case History: B sued in M in the QSC for breach of warranty – the damages awarded included a sum for loss of earnings for the period of 4 years after the purchase date since that was the period which it was expected to operate efficiently. M appealed to the FCSC who held that B could not recover for loss of profits after the condition of the engine was discovered in ’78. B appealed to the HCA against damage reduction Gibbs CJ: considered it a case of whether the B did what he could to mitigate the damage caused by bteach of warranty
Wilson, Deane and Dawson JJ: Characterised it as a case of determination of the point in time beyond which any damage suffered could not be said to be within the reasonable contemplation of the parties as flowing from the breach.
|
---|