Actions for debt
Debts and Liquidated Sums
“A debt recoverable under an indebitatus account was not and is not now conceived of simply as a cause of action for breach of a duty or obligation. In other words it is a mistake to regard the liability to pay a debt of a kind formerly recoverable in debt or indebitatus as no more than the result of a breach of contract...which the creditor must affirmatively allege and prove” – Young v Queensland Trustees Ltd (1956) 99 CLR 560
Requirements of an Action for Debt
Generally actions for debt only arise upon executed consideration - i.e. performance of the contract by the party claiming payment (e.g. price of goods sold and delivered) but sometimes it may be recovered as a debt/liquidated sum where payable on a fixed day whether or not consideration has been furnished (payment by instalments).
What amounts to sufficient performance of a plaintiff’s contractual obligations to entitle payment depends on the distinction between entire and divisible obligations and on the doctrine of substantial performance
Entire obligations – ones that must be wholly performed for the plaintiff to be able to entire any of the payment for performance specified in the contract – i.e. performance is a condition precedent to the defendant’s obligation to pay
Divisible obligations – contracts are likely to be divisible where work under the contract and its payment is divided by corresponding segments. Where it is divisible the plaintiff will be entitled to payment for each segment or part of the work fully performed.
Steele v Tardani (1946) 72 CLR 386 Facts: The plaintiffs were 3 Italian internees who had been released from internment and permitted to accept employment from the defendant. The plaintiffs weren’t employed to cut any specified amount but were paid at a price per ton and both were entitled to terminate at any time. The trial judge found that the contract was to cut the wood to certain specifications. He held that the defendant was liable to accept and pay for firewood cut into proper dimension and to pay fair price for other firewood because he had accepted the benefit of making the allowance for the cost of splitting some of the wood to the specifications. Issue: To what extent is the defendant liable to the plaintiff Ratio (Dixon J):
Latham CJ said that in order to recover, the plaintiffs have to claim upon a quantum meruit which can only be allowed on evidence of afresh contract – on this it is not sufficient that he sold the firewood, and the only way to defeat the claim is not if he allowed the firewood to decay on the ground. But agreed with the second set of evidence of Dixon J. |
Legislation
The right to payment for work under a contract not fully performed may be affected by legislation.
Nemeth v Bayswater Road Pty Ltd [1988] 2 Qd R 406 Facts: Under an agreement for hire of an aircraft the appellants agreed to pay $2,200/month payable at the end of each month. On 16th of February the aircraft crashed and the contract was frustrated. Issue: What are the appellants liable to pay Ratio (McPherson J):
|
---|
Substantial Performance
Where a party has substantially performed his/her obligations under the contract the doctrine of substantial performance may allow recovery of the contract price, less a payment of damages to the other party as compensation for incomplete work.
Hoenig v Isaacs [1952] All ER 176 Facts: The plaintiff was an interior decorator who was employed by the defendant to decorate a flat and provide it with furniture including a wardrobe and bookcase to the sum of 750. The plaintiff claimed to have carried out the work in compliance with the contract and demanded the balance of 350. The defendant alleged the work was performed negligently/unskilfully. The official referee held that the door of a wardrobe required replacement and the bookshelf was too short and had to be remade. He further held there was substantial compliance and the defendant was liable to 750 less loss of remedying defects Ratio (Somervell LJ):
Ratio (Denning LJ):
Order: Appeal dismissed |
---|
Bolton v Mahdeva [1972] 1 WLR 109 Facts: The plaintiff agreed to install a heating/hot-water system in the defendant’s home for 560. The defendant alleged the work was improperly done and that the plaintiff had wholly failed to perform the contract. The trial judge held the defendant was entitled to a set of 174.50 for the defects. There were other amounts to be taken into account and judgement was given to the plaintiff for 431.50. The defendant appealed. Ratio (Cairns LJ):
Ratio (Sachs LJ):
Order: Appeal allowed |
---|
In Zemperoni...